The city todayCycling and the Mobilitätsgesetz · as of September 2026
In 2016 campaigners gathered 105,425 signatures in three and a half weeks. Two years later Berlin passed Germany’s first Mobilitätsgesetz, a mobility law, and its cycle plan gave the city until 2030 to build the network. The Senate’s progress report for 2025, sent to the Abgeordnetenhaus on 12 August 2026, shows how far it has got.
Scroll from the petition to the streets
Cyclists fill a tree-lined Berlin street on the ADFC Sternfahrt, the cycling club’s annual ride from across the city to the Brandenburger Tor, 6 June 2021.Leonhard Lenz, 2021. Wikimedia Commons. CC0.
01The network the law demands
Every route below is in the cycle plan the Senate made binding in December 2021. The Senate counts what it finished on them from 2017 on; lanes that already existed before then are not in the count.

The Abgeordnetenhaus, Berlin’s state parliament, 2014. · Abghs, 2014. Wikimedia Commons. CC BY-SA 4.0.
14 June 2016
The Initiative Volksentscheid Fahrrad, a citizens’ campaign for a cycling referendum, collected 105,425 signatures in three and a half weeks (each dot stands for a hundred of them) and handed them in on 14 June 2016.
Source: Initiative Volksentscheid Fahrrad
28 June 2018
On 28 June 2018 the Abgeordnetenhaus, Berlin’s state parliament, passed the Berliner Mobilitätsgesetz, the first law of its kind in Germany.
Source: Berliner Mobilitätsgesetz · Initiative Volksentscheid Fahrrad
December 2021
In December 2021 the city’s cycle plan made the network binding. Its backbone is the priority network: 870.5 km of main routes across the city.
Source: Senate progress report 2022 · Radverkehrsplan · Senate progress report 2025
due 2030
Add the supplementary network, 1,527.8 km of local routes, and the plan comes to 2,398.3 km. Under the Mobilitätsgesetz it is to be built by 2030.
Source: Senate progress report 2025 · Radverkehrsplan
2017–2025
Each square is 10 km of planned route. By the end of 2025, the Senate counted 140.1 km of the network as newly built or upgraded since 2017: 5.84%.
Source: Senate progress report 2025
2017–2025
On the priority network, 78.2 km is done, 8.99%. On the supplementary network, 61.9 km, 4.05%. Five years remain before the deadline.
Source: Senate progress report 2025
02Fast lanes, then a stricter count
In 2020 25.9 km of temporary cycle lanes went down in seven districts. Two years later the Senate changed how it counts. Until 2021 a cycle lane on each side of a 1-km street counted as 2 km. Since 2022 it counts as 1 km. So totals from before 2022 cannot be set beside later ones.
One street, 1 km long, with a lane on each side



03The plan against the streets
The Radverkehrsplan, the city’s cycle plan, set a target for the network every year from 2022. Against it stand the Senate’s own reports of every cycle route finished, on the network or off it.
2022
The plan asked for 40 km of network in 2022. The city finished 26.5 km of cycle routes; 17.5 km of it on the planned network.
Source: Radverkehrsplan · Senate progress report 2022 · Berlinfographics fact-check
2023
The plan asked for 60 km of network in 2023. The city finished 26.0 km of cycle routes, less than the year before; 18.5 km of it on the planned network.
Source: Radverkehrsplan · Senate progress report 2023 · Berlinfographics fact-check
2024
The plan asked for 100 km of network in 2024. The city finished 23.6 km of cycle routes, less than the year before; 20.4 km of it on the planned network. On the network itself, that was the best year.
Source: Radverkehrsplan · Senate progress report 2024 · Berlinfographics fact-check
2025
The plan asked for 200 km of network in 2025. The city finished 21.2 km of cycle routes, less than the year before; 16.1 km of it on the planned network.
Source: Radverkehrsplan · Senate progress report 2025 · Berlinfographics fact-check
2022–2025
Added up, the plan asked for 400 km in four years. The city finished 97.3 km of cycle routes of every kind, about a quarter; on the planned network, 72.5 km.
Source: Radverkehrsplan · Berlinfographics fact-check · Senate progress report 2022 · Senate progress report 2023 · Senate progress report 2024 · Senate progress report 2025
04Lanes kept apart from traffic
On main roads the law asks for cycle lanes kept apart from cars, by kerbs or bollards, like the one on Tempelhofer Damm. The Senate’s reports count them separately: 7.5 km in 2022, 4.8 km in 2023, 8.2 km in 2024, 4.1 km in 2025.
Protected lanes finished each year, km


05The cycle superhighways
The Mobilitätsgesetz asks for at least 100 km of cycle superhighways, subject to available funding. Feasibility studies found nine routes, 134 km in all. In summer 2024 the Senate ended work on six of them for lack of money. The first, Königsweg – Kronprinzessinnenweg (about 14 km), was filed for planning approval at the end of 2025; that procedure takes at least 1.5–2 years. Built so far: 0 km.
The routes found feasible, and what became of them
Yellow: RSV 3 Königsweg – Kronprinzessinnenweg, filed for planning approval · struck through: shelved in summer 2024

06The money
These are the transport department’s cycling budget lines. Of the €82.4m available, €48.0m came from SIWA, the city’s investment fund, marked as money available from 2025 on. €19.5m was spent.

07Vision Zero
“Vision Zero”, the aim that no one should be killed or seriously injured on the roads, is one of the cycle plan’s three strategic goals. In 2025 the Senate counted 563 cyclists seriously injured and five killed.
Each mark is one cyclist, 2025

Berlin’s cycling law is still in force. Every year since 2022, the city has built less cycle route than the year before.
Press & citation
Free to publish under CC BY 4.0 — in print, online, on Wikipedia and in teaching, commercially or not — with credit to Berlinfographics and a link to this page.
Ready-to-use image
The infographic as one image: headline, key figures, chart, sources and credit, 2,400 × 1,350 px PNG. Please use it unedited.
Download landscape (PNG)
Square format
A 1:1 version for social media and narrow columns, 1,800 × 1,800 px.
Download square (PNG)
Portrait 4:5
For Instagram and LinkedIn feeds, 1,620 × 2,025 px.
Download portrait (PNG)Credit line
Berlinfographics (berlinfographics.com), CC BY 4.0
Citation
Berlinfographics (2026). “Berlin's Unbuilt Cycle Network, 2016–2025”. Berlin Experiences. https://berlinfographics.com/berlin-bicycle-infrastructure/
Wikipedia
{{cite web |title=Berlin's Unbuilt Cycle Network, 2016–2025 |url=https://berlinfographics.com/berlin-bicycle-infrastructure/ |website=Berlinfographics |publisher=Berlin Experiences |date=2026-11-06 |access-date=2026-11-06}}
Our infographics, charts and texts are licensed CC BY 4.0: free to republish, including commercially, with credit to Berlinfographics and a link. Photographs keep their own licences, named in each caption. How to credit
Topics: The Second World War · Cold War Berlin · Nazi Berlin · Persecution & the Holocaust · Weimar Berlin · Prussia & the Kaiserreich · Architecture & the built city · Culture, science & society · Reunified Berlin · Unusual facts
Contact: info@berlinfographics.com · Press: press@berlinfographics.com · Imprint · Privacy